The El Dorado City Commission approved the Ballpark Improvement Plan in December 2022, which includes upgrades at Central Fields, East Park Fields and McDonald Stadium.
Start Date: December 2022
Completion Date: 2024
Total Estimated Cost: $2.062 Million
December 2022 - City Commission approves use of Excess Sales Tax Dollars to fund a four-year ballpark improvement project
Spring 2023 - Request for bids for McDonald Stadium fence project
April 2023 - Request for proposal for Central and East Park Concession and restroom facilities
May 2023 - Concession and restroom project awarded to Conco Construction
June 2023 - Request for proposal for McDonald Stadium turf project
- McDonald Stadium outfield fence project awarded to Champion Wall Systems and Kansas Fencing
July 2023 - McDonald Stadium turf project awarded to Hellas Construction to replace infield turf
- Central and East park concession/restroom facilities in design process
August 2023 - Work begins at McDonald Stadium to replace turf
- McDonald Stadium fence in design process
- Construction begins on Central and East concession/restroom facilities
October 2023 - Anticipated construction of Hamblin Field fence replacement and bullpen addition
- Anticipated completion of McDonald Stadium turf
- Anticipated construction of McDonald Stadium fence
November 2023 - Anticipated completion of McDonald Stadium fence
December 2023 - Anticipated delivery of McDonald Stadium, East and Central scoreboard
- Anticipated completion of East Park concession/restroom facilities
January 2024 - Anticipated completion of Central Park concession/restroom facilities
February 2024 - Anticipated installation of McDonald Stadium scoreboard
Spring 2024 - Anticipated installation of Central and East scoreboards
- Anticipated completion of Hamblin Field fence replacement and bullpen addition
Fall/Winter 2024 (estimated timeframe) - At Central and East ballfields - backstops, shade structures, Orndorff bleacher pad and Central Park irrigation; at McDonald Stadium - facade updating, bleacher benches, building improvements, backstop
McDonald Stadium Project Expenses
Estimated Total $906,000
Estimated Actual
- Turf and Mound Replacement - $315,000 $335,500
- Outfield Fence - $200,000 $179,054
- Facade Updating - $150,000
- Bleacher Benches - $100,000
- Other Building Improvements - $96,000
- Scoreboard and Backstop - $45,000
Central Park Ballfield Project Expenses
Estimated Total $610,000
Estimated Actual
- Concession/Restroom Facility - $300,000 $299,974
- Field Fences - $225,000
- Scoreboards and Lighting - $36,000
- Backstops and Bullpens - $24,000
- Irrigation and Shade Structures - $25,000
East Park Ballfield Project Expenses
Estimated Total $546,000
Estimated Actual
- Concession/Restroom Facility - $300,000 $299,974
- Fences - $100,000
- Orndorff Bleacher Pad - $100,000
- Scoreboards (Orndorff & Snell) - $14,000
- Backstops and Bullpens - $12,000
- Shade Structures - $20,000
-
Community Impact